Turning an unused grass bank into a safer, more inclusive school entrance
When we first arrived on site, there was a steep grass bank and a large area of waste ground, neither of which was of any use to the school. We’ve now transformed it into a brand new 60m disabled access ramp for a local primary school, improving accessibility and creating a safer, more inclusive environment for pupils, staff and visitors.
The scheme took the site from raw ground to a fully finished route. It covered excavation into the bank, foundations, retaining walls, surfacing and edging, all built to a high standard and designed to last.
Cutting a 60m ramp into an existing bank takes careful planning and good groundwork. Our team worked through the excavation and foundation stages and then built up the walls and surfaces, and the result is a smooth, practical route that really does make a difference to everyday school life.
Key work undertaken
Excavation & groundworks
Excavating into the existing grass bank
Clearing waste ground and removing soil
Forming the ramp’s route and levels
Preparing the formation for concrete foundations
Foundations & retaining walls
Laying concrete strip foundations
Building blockwork retaining walls
Facing the walls in red brick, with brick-on-edge copings
Building a low brick dividing wall in the same style
Surfacing & finishing
Laying a smooth tarmac surface along the full length of the ramp
Fitting timber edging to the planting areas
Spreading topsoil, ready for landscaping
Handrails: bespoke handrails are currently being fabricated for the ramp
Another transformation completed by the TCS Plant team. Great work from start to finish by everyone involved, creating a lasting improvement for the school community.